Construction project on Yale delayed
| Updated: 2/07 10:59 am |
Published: 2/07 10:58 am
|
The multi-million dollar project to widen Yale has been delayed.
The project calls for Yale to be widened from four to six lanes from 61st to 71st. It was originally scheduled to be finished last July, but orange barrels are still up.
Crews say area utilities were not in the places the drawings showed so engineers have to make modification. The project should now be finished in March.
This delay will push back other projects.